| PEKERJAAN | TARGET | BOBOT | PROGRESS | REAL | AKSI |
|---|---|---|---|---|---|
|
A.
Area Pagar Mess Direksi - Belakang WHS 02/03 Tangki ROP
|
|
||||
|
1.
Pekerjaan bongkar pagar lama tangki ROP (60m x 2m)
|
- | 100.00% | 100% |
|
|
|
2.
Pekerjaan Sepatu beton
|
- | 100.00% | 100% |
|
|
|
3.
Pekerjaan pasang kembali pagar
|
- | 100.00% | 100% |
|
|
|
4.
Pekerjaan tapak
|
- | 100.00% | 100% |
|
|
|
5.
Pekerjaan Kolom
|
- | 100.00% | 100% |
|
|
|
6.
Pekerjaan Balok Sloof
|
- | 100.00% | 100% |
|
|
|
7.
Pekerjaan dinding bata
|
- | 100.00% | 100% |
|
|
|
8.
Pekerjaan dinding Plaster
|
- | 100.00% | 60% |
|
|
|
9.
Pekerjaan Ring Balok
|
- | 100.00% | 100% |
|
|
|
10.
Pekerjaan Pagar BRC
|
- | 100.00% | 90% |
|
|
|
B.
Area COM
|
|
||||
|
1.
bobok
|
- | 100.00% | 100% |
|
|
|
2.
Pekerjaan Sepatu beton
|
- | 100.00% | 100% |
|
|
|
3.
Pekerjaan pasang kembali pagar
|
- | 100.00% | 100% |
|
|
|
4.
Pekerjaan tapak
|
- | 100.00% | 100% |
|
|
|
5.
Pekerjaan Kolom
|
- | 100.00% | 100% |
|
|
|
6.
Pekerjaan Balok Sloof
|
- | 100.00% | 100% |
|
|
|
7.
Pekerjaan dinding bata
|
- | 100.00% | 100% |
|
|
|
8.
Pekerjaan dinding Plaster
|
- | 100.00% | 100% |
|
|
|
9.
Pekerjaan Ring Balok
|
- | 100.00% | 100% |
|
|
|
10.
Pekerjaan Pintu
|
- | 100.00% | 100% |
|
|
|
11.
Pekerjaan Pagar BRC
|
- | 100.00% | 90% |
|
|
|
C.
Area SEP
|
|
||||
|
1.
Bobok Gali
|
- | 100.00% | 100% |
|
|
|
2.
Pekerjaan Sepatu beton
|
- | 100.00% | 100% |
|
|
|
3.
Pekerjaan Pembuatan Pintu gerbang
|
- | 100.00% | 100% |
|
|
|
4.
Pekerjaan tapak
|
- | 100.00% | 100% |
|
|
|
5.
Pekerjaan Kolom
|
- | 100.00% | 100% |
|
|
|
6.
Pekerjaan Balok Sloof
|
- | 100.00% | 100% |
|
|
|
7.
Pekerjaan dinding bata
|
- | 100.00% | 100% |
|
|
|
8.
Pekerjaan dinding Plaster
|
- | 100.00% | 50% |
|
|
|
9.
Pekerjaan Ring Balok
|
- | 100.00% | 50% |
|
|
|
10.
Pekerjaan Pagar BRC
|
- | 100.00% | 70% |
|
|
|
D.
Pembuatan Pos Satpam
|
|